COBie data delivery

COBie deliverables to BS 1192-4, with asset data structured, populated and validated against the employer information requirements.

Discipline
Digital and BIM
Typical timescale
Populated through the design stages, delivered at each agreed exchange

WHAT IT IS

COBie — Construction Operations Building information exchange — is the structured handover of asset data: what was installed, where it is, what system it belongs to, who made it, and what the operator needs in order to maintain it. BS 1192-4 is the UK code of practice for it.

It is a data deliverable rather than a drawing deliverable, and it fails for data reasons. The common failure is not a missing model but an incomplete or inconsistent one: spaces not named to the client's own convention, systems not classified, types duplicated because two people named the same air handling unit differently, or fields populated with a placeholder that survives to handover.

WHEN YOU NEED IT

Where COBie is named in the employer information requirements — which on public sector work, higher education, healthcare and large commercial estates it usually is — and on any project where the client intends to load asset data into a CAFM or maintenance system after handover.

Worth raising even where it is not required: an asset register produced during design costs far less than one produced by surveying the building afterwards.

OUR PROCESS

The information requirements are read first, and the required fields are mapped to the model before anything is populated. COBie collected at the end from a model that was not built to produce it is a manual data exercise, and that is where the cost and the errors are.

Naming, classification and space data are agreed with the client and the lead consultant early — Uniclass 2015 unless the client's own system takes precedence — because renaming spaces and systems retrospectively invalidates every reference to them.

Deliveries are validated before issue rather than after rejection. The design-stage responsibility ends where the contractor's begins: SDE provides the design and type data, and the installed serial numbers, warranty dates and commissioning records come from the contractor.

DELIVERABLES

What you receive

  • COBie deliverable at each required exchange
  • Asset data field mapping against the information requirements
  • Space, zone and system naming and classification
  • Type and component data for MEP assets
  • Validation report before issue

STANDARDS

Standards applied

The editions in force at the time of design. Where a standard is amended mid-project we confirm which edition the appointment is based on.

  • BS 1192-4:2014Collaborative production of information — fulfilling employer information exchange requirements using COBie — code of practiceBSI
  • BS EN ISO 19650-1:2018Concepts and principlesBSI
  • BS EN ISO 19650-2:2018Delivery phase of the assetsBSI
  • Uniclass 2015NBS unified classification for the construction industryNBS
  • BSRIA BG 49Commissioning Building ServicesBSRIA

QUESTIONS

Common questions

What is COBie?

COBie stands for Construction Operations Building information exchange. It is a structured, non-geometric dataset covering the spaces and assets in a building — systems, types, components, locations and the attributes needed to maintain them — exchanged as a spreadsheet or IFC file. BS 1192-4:2014 is the UK code of practice defining how it is produced and delivered.

Who is responsible for COBie data on a project?

It is shared. The design team provides space, system and type information as the design develops; the contractor and specialist installers provide installed component data, serial numbers, commissioning records and warranty information. The information manager defines the requirements and validates deliveries. Responsibility is set out in the BIM Execution Plan.

When should COBie be started?

At the point the model is set up, not at handover. COBie is a view of data that already exists in the model, so a model built with the required naming, classification and parameters produces it almost as a by-product. Collecting it retrospectively is a manual exercise with a predictable error rate.